The Town of Carleton Place is reminding residents that construction schedules are subject to change due to weather, staffing, and material supply.
For the week ahead, crews will continue blasting and rock excavation at both the Water and Wastewater Treatment Plants.
Work on forming and installing rebar for the wetwell at the Wastewater Treatment Plant, as well as sanitary forcemain installation at the Water Treatment Plant, will also continue.
On Captain A. Roy Brown Boulevard and McEachen Drive, utility installation for streetlights is planned. Base course asphalt paving is expected early next week on both Charles and St. Paul Streets.
At the Findlay Avenue Pumping Station, the foundation has been poured, and work will continue on the floor and pads in preparation for building installation next week.
Construction is ongoing at the Industrial Avenue and Princess Street Pumping Stations, with electrical and structural work continuing on-site.